Abstract
This paper addresses the scheduling of jobs with sequence dependent setup times in a deterministic, static flowshop scenario. Four heuristics are described and compared with three benchmarks which represent generally practiced approaches to scheduling in this environment. Performance results are presented for a series of test problems taken from and comparable to those described in previous research. The results indicate that while sophistication does not necessarily lead to performance improvements, two of the proposed heuristics produce substantially better results than the other methods tested and merit consideration for implementation in practice.
| Original language | English |
|---|---|
| Pages (from-to) | 215-225 |
| Number of pages | 11 |
| Journal | Omega, The International Journal of Management Science |
| Volume | 20 |
| Issue number | 2 |
| DOIs | |
| State | Published - Mar 1992 |
Scopus Subject Areas
- Strategy and Management
- Management Science and Operations Research
- Information Systems and Management
Keywords
- flow shop
- heuristics
- scheduling
Fingerprint
Dive into the research topics of 'Heuristics in flow shop scheduling with sequence dependent setup times'. Together they form a unique fingerprint.Cite this
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver